Terminal Modernization Phase III

The airport is presently in the midst of Phase 3 of a four phase terminal modernization project. Phase 3 is the single largest project in it’s history – a $30.8 million, 54,000 square feet expansion. Phase 3 picks up where Phase 2 ended, right around the security checkpoint. All work done in this phase is post security. Construction on this portion of the project is expected to be complete in summer 2019.

Terminal Modernization Phase III Update

Sept. 11, 2018 – The new Gate 2 will open in the near future, followed by the opening of Gate 3. When Phase 3 is complete, it will all be one concourse: Gates 1 – 9. We will no longer use the “Concourse B and C.”

Until then, it will be Gates 2 and 3 AND Gates C1- C6. A temporary corridor will be used to access C1-C6.

In addition to the terminal construction, work continues on improvements to the terminal drive and the parking lots. Parking in short-term will be extremely limited throughout this project. The terminal entry way and parking lot is expected to be complete by mid-October.

Phase II

These photos show work done in Phase II, which involved the area pre-security.

Exterior photo of the CID terminal with the CID logo and "Everybody loves an upgrade" text overlaid.

Terminal Modernization Project – Phase I & II

Phase 1 of the Terminal Modernization Project at The Eastern Iowa Airport completed at the beginning of 2015 with a new facade to the terminal and weather protection/enclosure added to the covered walk in the parking lot.

Phase 2 of the project was completed in December 2016 and updated the interior space bringing in natural lighting, natural finishes, improved energy efficiency, and a modern look and feel.

More Exiting News

Pulling For Honor 2017

Pulling For Honor is a fundraiser benefiting Eastern Iowa Honor Flight. The mission of Eastern Iowa Honor Flight is to transport America’s veterans to Washington, D.C., to visit the memorials…

Win $500 in Airfare on Frontier Airlines

Head to Denver with The Eastern Iowa Airport! Pack your bags as Frontier Airlines’ seasonal nonstop flights to Denver are back and we’re celebrating by giving away $500 in airfare…

Airport Commission Approves Agreement with Uber

Iowa’s Creative Corridor – The Cedar Rapids Airport Commission has approved an agreement with the rideshare company Uber to operate at The Eastern Iowa Airport. The Commission approved the one-year…
Menu

Important information about COVID-19 and CID's proposed Travel Well initiative. Click here for details.

X